The MSEC Geothermal Conductivity Test measures the amount of the on site 'ground source energy asset' available for use by a geothermal heat pump system. These tests are used for larger commercial applications, and is recommended to be conducted before any system design is attempted.
The 48 hour MSEC Geothermal Conductivity Test is run per (strict) G.R.T.I.
specifications. Data from the test is downloaded to GRTI within 1 working day
from completion of test, with full report delivered to client within two weeks of completion of test. (see report below)
A full test includes the following materials,
drilling, and labor:
1. Utility marking by JULIE.
2. Bore up to 300 foot vertical bore with a diameter
of up to 6 inches. Depths in excess of 300 feet are done
on a per foot basis.
3. Install HDPE u-bend geothermal loop up to 610 feet
at 1 inch in diameter.
4. Grout to 1.0 conductivity using a mix of one part
Thermal Grout Lite with five parts Badger geothermal
silica sand.
5. Allow installed loop to adjust back to pre-existing
temperature by waiting seven days before the test begins.
(Heat is created by the drilling process.)
6. Attach pump, heaters, and GRTI data logger to the
loop to record the estimated average heat capacity (Btu/cubic
ft degrees F), thermal conductivity (Btu/hr-ft-degrees
F.), and estimated thermal diffusivity (square ft/day).
7. Run test uninterrupted for 48 hours.
8. Time to complete the analysis is approximately two
weeks after the field test is complete.
9. MSEC supplies written report. Report Example.
Spoils from the drilling are left on site, but clean
up of bags, pallets, and all other construction debris
is included. The test loop can be incorporated for use into the
loop field. Copy of drillers
log provided.
Conductivity Test Site Photos.
Questions?
Call MSEC today with no obligation!
309.764.1111. Or email us.
|